Nebulae Solutions LTD.

Home › Flow assurance engineering

Flow assurance engineering

Keeping oil and gas moving from reservoir to plant, safely and economically, for the whole life of the field. This page explains the science behind each threat to flow and how we manage it in practice.

  • Hydrates
  • Wax
  • Asphaltenes
  • Scale
  • Corrosion
  • Pigging
  • Operations support
Pigging, hydrate and wax control

What flow assurance covers

Flow assurance is the engineering discipline that keeps hydrocarbons moving from the reservoir, through wells, flowlines and risers, to the processing plant. It deals with anything that can restrict or stop flow: solids that form from the fluids themselves, the way gas and liquid share a pipe, and the damage fluids do to the pipe over time.

Most problems come from the same root cause. Reservoir fluids leave hot, high-pressure conditions and travel through cold, often subsea, pipework. As temperature and pressure fall, the fluids cross phase boundaries: water and gas can form hydrates, heavy paraffins crystallise as wax, asphaltenes fall out of solution and dissolved minerals precipitate as scale.

ThreatWhat formsMain triggerTypical consequence
Gas hydratesIce-like crystals of water and gasHigh pressure, low temperature, free waterSudden blockage, safety hazard
WaxCrystallised heavy paraffinsWall temperature below wax appearance temperatureGradual restriction, gelling on shutdown
AsphaltenesHeavy, polar aggregatesPressure falling towards bubble point, gas injection, blendingDeposits in wells and equipment
ScaleMineral salts (carbonates, sulfates)Mixing incompatible waters, CO2 loss on pressure dropRestriction of tubing, valves, chokes
CorrosionMetal lossCO2, H2S, oxygen, water wettingLoss of containment over time
SluggingLarge liquid slugsTerrain, risers, low gas ratesTrips, vibration, separator overload

Our focus is on solutions rather than simulation alone. Models tell you where a problem might appear; we turn that into chemical choices, operating limits, procedures and monitoring that operations teams can rely on.

Gas hydrates: theory

Gas hydrates are crystalline solids in which water molecules, linked by hydrogen bonds, form cages that trap small gas molecules such as methane, ethane, propane, CO2 and H2S. They look like ice but can form well above 0 °C when the pressure is high enough. Three structures are common: structure I (sI) with small guests such as methane and CO2, structure II (sII) which also accommodates propane and isobutane and is usually the most stable form for natural gas, and structure H (sH) with larger molecules.

For any gas composition and water salinity there is an equilibrium curve: at a given pressure, hydrates are stable below a certain temperature. Operating to the left of that curve (colder or at higher pressure) puts the system in the hydrate region. The distance into that region is called the subcooling.

Subcooling

ΔTsub = Teq(P) − Top

Teq(P) hydrate equilibrium temperature at the operating pressure, Top actual fluid temperature. A positive value means the system is inside the hydrate region; the larger it is, the stronger the driving force for hydrates to form.

Hydrate formation has two stages. Nucleation is the random, stochastic appearance of the first stable crystal nuclei, often after an induction time. Growth then follows, and in a pipeline the particles agglomerate and stick to the wall until a plug forms. Formation is fastest at the water–hydrocarbon interface, and is promoted by turbulence, high subcooling and free water.

Why plugs are dangerous. A hydrate plug can hold a large pressure difference. If it is depressurised from one side only, the plug can break free and travel at high velocity, damaging pipework. Plugs are remediated by careful, usually two-sided depressurisation, with heat or chemicals where appropriate.

Hydrate prevention strategies

Every hydrate strategy does one of three things: keeps the system outside the hydrate region, slows formation down for long enough, or stops particles from sticking together.

StrategyHow it worksStrengthsLimitations
Thermodynamic inhibitors (methanol, MEG)Shift the equilibrium curve to lower temperatureRobust and well understoodHigh volumes (often 20–60 wt% in water), logistics, recovery and losses
Kinetic hydrate inhibitors (KHI)Water-soluble polymers delay nucleation and growthLow dose, typically 0.5–3 wt% in waterLimited subcooling and hold time; can precipitate at high temperature
Anti-agglomerants (AA)Surfactants let hydrates form but keep them as a transportable slurryCan handle high subcoolingNeed a liquid hydrocarbon phase and work up to a limited water cut
Thermal managementInsulation or heating keeps fluids above TeqNo chemicals in steady stateCooldown during shutdown, high capital cost for heating
DepressurisationLowers pressure below hydrate pressure at ambient temperatureEffective for shutdowns and remediationNot always possible, especially with deep-water liquid heads
Water removalDehydration of gas before transportRemoves the causeApplies to export gas rather than multiphase lines

Hammerschmidt equation

A simple first estimate of the temperature shift produced by a thermodynamic inhibitor is the Hammerschmidt equation. It is useful for screening and for sense-checking injection rates, but design work uses rigorous thermodynamic models.

Hammerschmidt (temperatures in °C)

ΔT = 1297 · W / [ M · (100 − W) ]

ΔT depression of the hydrate temperature, W inhibitor concentration in the water phase (wt%), M molar mass of the inhibitor (methanol 32.04 g/mol, MEG 62.07 g/mol).

Inhibitor screening calculator

Hammerschmidt estimate for screening only. Not for design: salts, high concentrations and inhibitor losses to the gas and hydrocarbon phases all need a proper thermodynamic model.

Temperature depression at that concentration–
Concentration needed for that margin–

Under-inhibition: the common failure

Most hydrate incidents in inhibited systems are not caused by a wrong design, but by the inhibitor concentration in the water falling below what the design assumed. Typical causes are rising water production, injection pump or umbilical failures, inhibitor partitioning into the gas and condensate, and a wrong assumption about salinity. That is why we put so much weight on monitoring the real concentration in produced water.

Wax deposition

Crude oils and condensates contain long-chain paraffins (n-alkanes, typically above about C18). As the oil cools below its wax appearance temperature (WAT), these molecules crystallise. In a pipeline the wall is colder than the bulk fluid, so wax forms and sticks there first.

The dominant deposition mechanism is molecular diffusion: the radial temperature gradient creates a concentration gradient of dissolved wax, and wax molecules diffuse towards the cold wall where they come out of solution.

Molecular diffusion of wax to the wall

dm/dt = ρw · Dm · A · (dC/dT) · (dT/dr)

dm/dt wax deposition rate, ρw wax density, Dm diffusion coefficient of wax in oil, A deposition area, dC/dT wax solubility gradient with temperature, dT/dr radial temperature gradient at the wall.

Deposits trap oil inside them and age over time: lighter components diffuse out and the wax content rises, making the deposit harder and more difficult to pig. Below the pour point, a waxy oil can gel during a shutdown, and restarting the line then needs enough pressure to break the gel.

How we manage wax

  • Measure WAT, pour point, gel strength and deposition rate on representative samples.
  • Set pigging frequency from the predicted deposition rate, so deposits never become too thick or hard to remove safely.
  • Select and qualify wax inhibitors and pour point depressants where they add value.
  • Define shutdown and restart procedures, including flushing or displacement where gelling is a risk.
  • Plan remediation: hot oil, solvents or mechanical removal when deposits have built up.

Asphaltenes

Asphaltenes are the heaviest, most polar fraction of crude oil. They are kept in suspension by resins. When the balance is upset, they aggregate and deposit, typically in production tubing near the depth where reservoir pressure falls towards the bubble point. Below the bubble point, light ends leave the oil and asphaltenes often become stable again, which gives an asphaltene onset pressure window to manage.

Gas injection (including CO2), commingling of different crudes and acidising can all destabilise asphaltenes. Screening uses SARA analysis and correlations such as the de Boer plot; definitive work uses onset pressure measurements on live oil.

Mitigation options are dispersants and inhibitors injected downhole, operating outside the onset window where possible, and periodic solvent (for example xylene) treatments.

Scale

Scale is the precipitation of mineral salts from produced water. The two most common routes are:

  • Sulfate scales (barium, strontium and calcium sulfate) when sulfate-rich injection water such as seawater mixes with formation water rich in barium and strontium.
  • Carbonate scale (calcium carbonate) when pressure drops and CO2 leaves the water, raising its pH. This is also a key issue in MEG systems, where pH stabilisation and MEG regeneration change the water chemistry.

Saturation index

SI = log10 ( IAP / Ksp )

IAP ion activity product of the dissolved ions, Ksp solubility product at the same temperature and pressure. SI > 0 means the water is supersaturated and scale can form.

Scale inhibitors, mostly phosphonates and polymers, work at very low concentrations by blocking crystal nucleation and growth. Each system has a minimum inhibitor concentration (MIC), found by testing, which sets the dose or squeeze treatment design.

Corrosion

Internal corrosion of carbon steel lines is driven mainly by CO2 (sweet corrosion), H2S (sour corrosion) and oxygen, wherever water wets the steel. A classic estimate of the CO2 corrosion rate is the de Waard–Milliams equation:

de Waard–Milliams (1975)

log10 Vcorr = 5.8 − 1710 / T + 0.67 · log10 pCO2

Vcorr corrosion rate (mm/year), T temperature (K), pCO2 CO2 partial pressure (bar). It gives a conservative, unprotected rate; modern models add pH, flow, protective scales and inhibition.

Control relies on film-forming corrosion inhibitors, pH stabilisation in MEG systems, material selection and monitoring. A point often missed is chemical compatibility: corrosion inhibitors, KHIs, AAs and scale inhibitors can interfere with each other, so we test them together.

Pigging

Pigs are devices pushed through a pipeline by the flow to clean, gauge, inspect or separate fluids. In flow assurance they are used mainly to remove wax and liquid inventory.

Foam pigs

Low risk of sticking; used for first runs and lines with unknown deposits.

Cup and disc pigs

Good sealing and cleaning; bi-directional versions can be reversed.

Bypass pigs

Let some fluid through to keep wax ahead of the pig dispersed and avoid a wax plug.

Gel pigs and intelligent pigs

Gels for difficult cleaning; in-line inspection tools for wall thickness and corrosion.

The biggest risk is letting deposits build up too far before pigging: the pig then pushes a large volume of hard wax ahead of it and can stick. Pigging frequency, pig selection and launching and receiving procedures should be based on measured deposition rates, not habit.

Multiphase flow, shutdown and restart

In multiphase lines, gas and liquid travel at different speeds. Low gas rates, terrain and risers can cause slugging, where liquid builds up and is pushed out in large slugs. Liquid inventory also changes with flow rate, which matters when ramping up production.

Shutdowns are where many hydrate and wax problems begin. The fluid cools towards seabed temperature; the cooldown time is how long it takes to reach the hydrate temperature, and the no-touch time is the period in which operators can act without preservation steps. After that, the line must be protected, typically by depressurising, displacing or injecting inhibitor, before restart.

  1. Before shutdown: confirm inhibitor stock and injection availability, and know the cooldown and no-touch times.
  2. During shutdown: preserve the line in time (depressurise, inhibit or displace) and monitor pressures.
  3. Restart: inject inhibitor ahead of and during restart, ramp up in steps and watch for pressure-drop signs of restrictions.

Operations support and monitoring

Flow assurance strategies only work if the field operates the way the design assumed. Our operations support turns live data into clear actions.

  • Data reviews: process historian (PI) data on pressures, temperatures, water production and chemical injection, compared with design limits.
  • Inhibitor margin tracking: required versus actual inhibitor dose, kept up to date as water production changes.
  • Produced water monitoring: measuring inhibitor concentration and salinity. Because conductivity and acoustic velocity respond differently to salt and to inhibitor, measuring both gives two equations for two unknowns, and so the real hydrate safety margin in the water reaching the plant.
  • Meetings and reporting: regular operations and flow assurance meetings, with clear recommendations and owners.
  • Troubleshooting: pressure-drop increases, suspected restrictions, injection system faults and unexpected chemistry.
  • Procedures and training: start-up, shutdown, preservation and pigging procedures that operators can follow under pressure.

How we work

  1. Understand: fluids, water chemistry, design basis and operating history.
  2. Test: laboratory work where the answer depends on the actual fluids and chemicals.
  3. Recommend: limits, chemicals, doses and procedures with the reasoning behind them.
  4. Implement: support field trials, changes and start-ups.
  5. Monitor: track performance and adjust as the field changes.

Talk to us about flow assurance engineering

Tell us the problem or the question you need answered. We reply to every enquiry.

Email info@nebulaesolutions.com